PCI locked in. Another investment delivered, and the best is still to come 🌱

For first home buyers and investors in Perth, one of the most common questions is how long it really takes to go from land settlement to practical completion, and what needs to happen for it to move this quickly.

Karla and Stuart’s Yanchep investment property has officially reached Practical Completion Inspection, led on site by Jimmy, our Construction Supervisor.

From land settlement to PCI in 10 months, this is what happens when process leads and promises don’t.

✅ Land Settlement: March 2025
✅ Building Permit: April 2025
✅ Slab: May 2025
✅ Brickwork: July 2025
✅ Lockup: September 2025
✅ PCI: January 2026

What’s Next? A Community Still Growing 

While this home has reached practical completion, the journey doesn’t end here. The surrounding community continues to take shape, with future parkland and amenities planned by the land developer, adding even more appeal and long-term value to the area.

Thinking About Building an Investment in Perth?

If you’re serious about building an investment property in Perth, start with a team built for it, one that understands timing, process and the bigger picture beyond handover.

From land settlement to slab pour, PCI and beyond, we’re here to help you move forward with confidence.

Want to explore your own investment house and land package?

Learn More

B1 Homes