For first home buyers and investors in Perth, one of the most common questions is how long it really takes to go from land settlement to practical completion, and what needs to happen for it to move this quickly. Want the answer? Speak to our team today.
Karla and Stuart’s Yanchep investment property has officially reached Practical Completion Inspection, led on site by Jimmy, our Construction Supervisor.
From land settlement to PCI in 10 months, this is what happens when process leads and promises don’t.
✅ Land Settlement: March 2025
✅ Building Permit: April 2025
✅ Slab: May 2025
✅ Brickwork: July 2025
✅ Lockup: September 2025
✅ PCI: January 2026
If you’re serious about building an investment property in Perth, start with a team built for it.